St. Mark CES- renovation- Blood, Sweat and Tears

0 Comments

“Is there a doctor in the house” blood pressure is running high! Very busy today as we have plenty of activity, Below, our plumbers are placing underground pipe. We are scheduled to pour our SOG this Friday. Stay tuned as we rebuild! Floor for food nutrition room also to be poured Friday! We need door […]

St. Mark CES- construction progress

0 Comments

July 10, 2018 https://viewer.hangar.com/360?productId=Nr7w29nr 15 days later July 25, 2018 https://viewer.hangar.com/360?productId=O0wpa6kY Roofers are onsite- rooftop units arrive Monday site services (excavation) soon complete Topsoil being removed near portables- gravel arriving soon allowing  re- location of portables Foundation walls being built (addition) plumbers to install underground’s ASAP.     https://larryarbuckle.com

St. Mark CES- renovation – The Beat Goes On!

0 Comments

We are building the wall for The food nutrition room- plumbers are installing undergrounds. Footings are now ready for building foundation wall. Plumbers need to install all underground’s. Once installed will bring on SOG. Masonry contractor is starting foundation walls tomorrow. Gas meter has now been removed allowing our pipe to enter the building. We […]