Bishop Reding CHS- today’s visit

Work is progressing well as we push completion prior to Sept 4th

All ceilings / main floor/ have been opened up to receive heat pumps. I am told all ceilings / receiving heat pumps/ will be opened by end of week

Entrance to washrooms / doors/ have been removed.

Heat pumps and light fixtures being stored – gym

I am told doors arrive end of this week! Electricians are onsite