Demolition continues as we push to complete this task by next week🐌🐌

Mirage is in the library re- steel

All ceilings are down allowing sprinkler contractor to finish

Note: curbs for RTU arrive today or tomorrow! Steve ( metal duct contractor ) will place ASAP. Once placed we will cut openings. George R (our roofer) please follow along as we need you to watertight! You’re the guy👍

Site services has now started!