Steel has arrived ( Mirage) re- roof top units๐Ÿ‘๐Ÿ‘๐Ÿ‘

Steel is being placed( RTU) erector is placing steel

Mechanical Room- demolition near completion

Electrical distribution panels are onsite.

We still need gas meter removed to allow sprinkler and water pipe to enter building.๐Ÿข๐Ÿข

Footings re- additions are now ready for forming. I am told contractor will be onsite tomorrow.

Curbs are being built and then placed. By end of week ready to roof (watertight) curbs. Roof Top Units arrive July 30th. ๐Ÿ‘€