St. Mark CES- today’s update

We are pouring SOG on Wednesday/ addition / food Nutrition room/ and hallway entrance – east/

Also note: portables are being relocated

Hollow metal frames are onsite

Note: To all trades- we are framing all hallways /T Bar/ starting August 20th: please ensure all work / above ceilings/ is complete. That gives you 2 weeks!💋💋

https://larryarbuckle.com

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: