We are pouring SOG on Wednesday/ addition / food Nutrition room/ and hallway entrance – east/

Also note: portables are being relocated

Hollow metal frames are onsite

Note: To all trades- we are framing all hallways /T Bar/ starting August 20th: please ensure all work / above ceilings/ is complete. That gives you 2 weeks!💋💋