St. Mark CES- The final push

To all trades/ as agreed by everyone: starting Aug 22nd @ 7 am the T-bar gang are returning to complete all ceilings. Make sure all your wall penetrations are sealed above ceilings. Also, All units are hung and piping insulated. Fire verification happens on Monday the 27th and all ceilings should be fully tiled. We do not want to run anyone over so be prudent and get your work done. Also: do not lose sight of the addition as we are moving at a lightning pace. We are pushing completion/ addition/ prior to Christmas. ⛄️⛄️⛄️⛄️⛄️⛄️

https://larryarbuckle.com

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: