St. Nicholas CES- pre construction

St. Nicholas CES- pre construction

St. Mark CES- construction update

Stage: Sprinkler contractor has now placed their pipe! We await the return of our drywall contractor (Cannan) installing grid. Once installed allows the placement of lights, sprinkler heads and diffusers! Precast arrives Monday! I am told hollow metal frames (doors) arrive tomorrow! Also needed lintels ( galvanized) and plates! “Lead, Follow Or Get Out Of

St. Mark CES- precast arrives Oct 1st

This project will be firing back up Oct 1st as we are scheduled for precast! Once placed, sprinkler and plumbing pipe can be hung as well as electrical conduit! As discussed, we are pushing for a Jan 1st 2019 completion! Ensure all material is onsite! Stage area: sprinkler line re- drops to be complete this

St. Mark CES- awaiting precast

Pre- cast has been delayed (2nd floor) until the first week of October! That being said: going forward please ensure all material is onsite starting with: -All remaining hollow metal frames (doors) are onsite ( TRP) – all Lintels (galvanized) and plates be onsite (Mirage) – all open web joist and metal deck to be

St. Mark CES- awaiting precast

We have scheduled Oct 5th as are precast drop. The school has  scheduled a P.A. Day resulting in teachers and students not being onsite. TRP and PSI please connect Also note: once precast is placed / load bearing masonry walls to be complete 2-3 weeks [2nd floor to roof]. Following close behind we need open

St. Mark CES- construction progress

We are pushing to complete addition prior to Christmas. Gymnasium- starting to install metal duct. Lights and fans to follow. We are scheduled for completion / 2-3 weeks. Construction progress – south- west corner Construction progress north-east corner Construction progress north-west corner https://larryarbuckle.com