St. Mark CES – Closing in soon!

Soon, we will be closing in. Floor topping [2nd floor] has been poured. Metal deck [roof] will be spread tomorrow. Wooden parapet can start on Wednesday. Masonry contractor is onsite erecting interior walls. Installation of Windows starts next  Monday. Painters are on deck [block filler]

 

Once windows are  installed / bring on the brick veneer. Waiting for the Retaining Wall [TRP]. 

Curbs [RTU] arrive this week. GRRC [ our roofing company] stay tuned. We are pushing to be watertight prior to DEC 1st.

 

 

Floor topping [2nd floor] now complete