St. Mark CES- waiting for our roofer

0 Comments

Plywood parapet near completion! Curbs (RTU) are in place. / curbs for exhaust fans to be placed.Waiting for roof drains and M&E cones! Looking for GRRC ( our roofer) for Monday👍👍 Retaining Wall is ongoing and scheduled for completion – early next week. Mike (Wesley Paving) you’re on deck for sidewalk / mid next week! […]

St. Mark CES- preparation (roof)

0 Comments

As discussed at yesterday’s site meeting, we are installing plywood (parapet) and placing curbs (cones) for roof top units! Once these tasks are complete will bring on our roofer- hopefully end of this week or Monday / at the latest! Pic below was taken yesterday! I will be returning Thurs (pm) to record progress and […]

St. Mark CES – Nov 12, 2018 update

0 Comments

The weather forecast appears  favourable for the next 2 weeks. We are installing plywood for our parapet [roof] and pushing for the start of our roofer [ end of the week] We should start thinking of interior heat [ASAP]     We are starting our parapet wall [ plywood] and should be complete by tomorrow. […]