As discussed at yesterday’s site meeting, we are installing plywood (parapet) and placing curbs (cones) for roof top units! Once these tasks are complete will bring on our roofer- hopefully end of this week or Monday / at the latest! Pic below was taken yesterday! I will be returning Thurs (pm) to record progress and report. We need to be watertight ASAP!

Masonry block placed for lift ( stage)