St. Nicholas CES- plumbers worked all week-end

Plumbers worked all week-end allowing slab on grade to be poured this week! Keep masonry contractor going! Everstrong to install expansion joint, poly and re-bar/ for interior walls! 🎯🎯

Work continues! We are pushing slab on grade to be 100% complete prior to May 1st

Site Services now on deck

Where are we with precast???????