St. Nicholas CES- construction progress April 18th

Note: Permit Drawings ( Site Service ) are now onsite/ construction trailer!

We are pouring slab on grade / classrooms/ Monday! We are pushing 100% SOG prior to May 1st!

Waiting for Steel Columns followed by precast!πŸ‘€πŸ‘€πŸ‘€πŸ‘€πŸ‘€

Video below shows progress to date!