St. Nicholas CES – Electrical Duct Bank

As per discussion on site today: It was revealed/ now would be a good time to remove existing elec duct bank and replace with new- prior to precast. I am told Everstrong to remove existing elec duct and CEC build a new elec duct. Please initiate the paperwork allowing this task to be complete ASAP. Let’s take advantage of the lull before the arrival of precast [mid May]

We are still pushing / pouring SOG / scheduled for this Thursday [ weather permitting]

Below: video of construction progress to date:

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.