Cafeteria- footings have been poured- forms to be removed

foundation wall to be formed/ full length of existing cafeteria!

General contractor confirmed : areas around cafeteria and front addition to be level! This would allow the safe operation of machinery e.g zoom boom! Mario ( masonry contractor) is on Deck! Pushing for Tuesday/ all concrete footings need to be complete ASAP