St. Mark CES- update

Scott and I discussed expediting the work as follows:

– remove all fencing and material
-remove portables ASAP and make good surface below!

Perhaps we can move up schedule / asphalt paving

The rationale is “let’s do it now rather than later”

We can discuss at next site meeting!

Remove fence and clean up all areas

Make Good all surface areas complete with sod!

Prepare surface and sod areas around childcare!