St. Nicholas CES – update – Oct 3

0 Comments


All exterior window frames scheduled to be installed Monday

Exterior Glass to be installed following Thursday and Friday.

Ceramic tile starts next week- hallways.

We need heat !!!!

Lead, Follow or get out of the way

Pushing for T-bar ceilings
Need metal doors hung!
Starting exterior next week
🎯🎯🎯
Ongoing
ASAP

Walk-thru

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.