St. Nicholas CES- 63 days remaining

0 Comments

Arrowhead Paving is now on our critical path. 🎯🎯
Aerloc is onsite installing glass👍
The building needs a major clean up.
Brick veneer starting in the front.
Roof is only 45% complete. This has been a long process.
Arrowhead Paving starts next week.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.