St. Nicholas – 51 days remaining

51 days remaining
Millwork has arrived and being placed in the rooms
Everstrong preparing exit / frost slab
Remember: t-bar ceilings start / Nov 1st/ all work above needs to be complete. No whinning allowed after Nov 1st.
Everstrong to grind all floors prior to the return of ceramic tile contractor- next Wed! After we swept the floor many areas were discovered – to be levelled.Grinder
example of just one area to be repaired – grinder
Natural Gas Contractor is onsite starting installation of gas line. Arrowhead Paving -scheduled for tomorrow.
Where is Flynn Roofing?????

Video below shows progress as of March 14th. Starting our footings