St. Nicholas – 49 days remaining

Communication duct bank- now installed- looking out front entrance
Communication duct bank- looking from the road.
Gas main now installed
Contractor connecting gas main to building- Who is chasing the gas meter??
Note: Grinder needed all floors and levelled prior to flooring contractor’s arrival next Wed. Everstrong.
Delivery of Millwork now complete/ installation starts Monday.. Arrowhead Paving scheduled Monday- stringing curb lines. Flynn Roofing to watertight mechanical room [NOW]. T-Bar ceilings start next week. All work above to be complete. Consultants needed re- inspection above ceilings. Who is chasing the water meter.???
The Push is on.