Communication duct bank- now installed- looking out front entranceCommunication duct bank- looking from the road. Gas main now installedContractor connecting gas main to building- Who is chasing the gas meter??Note: Grinder needed all floors and levelled prior to flooring contractor’s arrival next Wed. Everstrong.Delivery of Millwork now complete/ installation starts Monday.. Arrowhead Paving scheduled Monday- stringing curb lines. Flynn Roofing to watertight mechanical room [NOW]. T-Bar ceilings start next week. All work above to be complete. Consultants needed re- inspection above ceilings. Who is chasing the water meter.???The Push is on.