St. Nicholas CES- 32 days remaining

2nd floor- waiting for ceramic tile Contractor./ floor/. Lockers scheduled – Dec 2nd.
Waiting – all classrooms ready for sheet goods.
2nd floor ceiling adjacent to washrooms ready to be framed followed with boarding.
2 heating units have been fired up. Inside now warm and toasty.
Starting installation metal duct – Gym
I Beam has now received spray /fire. We are boarding /ceiling/ Wed.

We are coming together On the inside but /Arrowhead / we need you on the exterior. The forecast – end of this week and next Is favourable re- Concrete curbs, sidewalks and asphalt. May the force be with you. We are going in the right directionđź‘Ť