Bishop Reding- heading towards the roof! Nov 13/19

Weather next week appears to be on our side. Knowing Mario he will “slam dunk” the 2nd floor in 2-3 weeks. Hopefully all lintels and bearing plates are All onsite. OWSJ / roof/ needed first week of Dec. Mirage Steel is in the batter’s cage.

Lintels onsite.
Scaffold now in place re- 2nd floor
View from the 2nd floor looking into courtyard
Snow removal needed – 2nd floor
Footings Cafeteria- ongoing