M M Robinson – Nov 14/19 construction update

Floors cafeteria scheduled for installation- next week. New Cafeteria scheduled for completion prior to Christmas.
Masonry contractor setting up – placement of block. Winter Heat may be required.
3 story addition- steel re- stairs have arrived.