St. Nicholas – 29 days remaining- can you feel it?

29 days remaining. Fire Verification scheduled Dec 9th. All ceilings must be in place allowing placement of fixtures.

Taping of ceilings has now started.
Elevator is being installed.
Base re- poles for parking lighting – being installed.
Folding Doors – Stage – being installed.
Here we go. Arrowhead Paving arrives tomorrow to begin our parking Area.
We will have live coverage.

Stay with us and watch a sea of mud transform into a beautiful parking Area -Updates daily. Can you feel it??

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.