St. Nicholas – 21 days remaining

0 Comments

Note:

All ceiling tile to be placed /in grid / starting Dec 2nd. Ensure all work is complete including inspections above – prior.

Locker installation start Dec 2nd

Fire Verification Dec 9th

ceramic tile /hallway/ ongoing.

Gym- the guys are working this week-end installing lighting and metal duct. We need Millwork installed in the library and admin office. We are painting the gym next week!
Early next week we are placing base asphalt / complete with lines/ in All parking areas. This will show we are open for business. DrainLand needed To upfill behind curbs.
All curbs have been poured
Fence needed childcare
North Parking
Mounds of dirt to be removed. Let’s use what we can onsite.