St. Nicholas – 20 days remaining

0 Comments

Fence needed – kindergarten play area
Backfill behind curb needed. We have plenty of topsoil onsite / to complete this task. Area behind curbs -cut to sub grade.
Aerloc needed to install glass fire separation stage [as per above] also all exterior doors and windows.
Flooring- ceramic tile and sheet goods are of concern. Hopefully Zetmaster Flooring can provide more manpower as Max [ on his own] will not be able to complete in 20 days. As per above picture ceramic tile / washroom walls / need to be installed / ASAP/ allowing installation plumbing fixtures / sinks
As scheduled. All above ceiling work needs to be complete prior to Dec 2. All ceiling tile -scheduled to be placed after the 2nd.