St. Nicholas – Dec 4th update
Where is Arrowhead Paving???
What are we doing with rear entrance???Typical hallway! Cleaners are now onsite and will remain until completion! Classroom doors soon to be installed complete with hardware.Patching of floors continues allowing placement of sheet goods. I recommend additional manpower being applied / due to our aggressive schedule.
Still, some rooms/floor/ will be skimmed in full.
General Contractor to ensure all rooms are swept and remain clean.
Millwork / Kor/ we are need all counters. Plumbing contractor to install sinks.Ceramic tile being placed in washrooms. Once placed allows installation of plumbing fixtures / sinks/Urgent! We need admin office up and running ASAPAVB contractor now onsite applying spray.Sprinkler coverage still required [2] stairwellsMillwork /Kor/ where are you ???