St. Nicholas- Dec 5th- It’s coming together.

Arrowhead is onsite preparing base. Asphalt scheduled for tomorrow
General contractor to clean all rooms ahead of flooring contractor. I am told flooring contractor will have more manpower next week
All windows / main floor/ also may need Insulation stuffed [header] preventing loss of heat.
Admin Office is now painted waiting for T-bar ceiling.
Hollow Metal Screen is now onsite / separating library from entrance / awaiting installation.
Masonry contractor trimming out elevator doors
We need to adjust size of sinks.