Asphalt arrives tomorrow to complete this task. Aerloc now onsite installing doors and windows. north-west cornerlooking into kindergarten play area – fence posts installed
front entrance doors now installed
Exit doors now installed
frame – fire separation re- stage now installed.Classroom Doors. Next Monday school board will be providing cleaners and start cleaning classrooms. Once a room is cleaned – door will be shut preventing access into the room. We need doors installed complete with hardware.