St. Nicholas – Dec 12- update

Asphalt has now been placed. Tomorrow, lines to be painted .Exterior doors and glass have been installed “Yeah Aerloc”. Poles re- Lighting / parking area/ now being installed.
Asphalt placed in play area
sinks and toilet partitions being installed / washrooms.
Many floors are being skim coated/ classrooms
classroom doors are being hung complete with hardware. glass needed
Admin office is now ready for flooring ASAP
Glass fire separation / stage/ has been installed. Sprinkler protection has been installed / zoom in/