St. Nicholas- Dec 14- update

Always a Nice Day at St. Nicholas- Line painting now complete
Next week the front foyer will be the battle zone. Trades are exiting out the front entrance. Could get ugly!!!!
Admin office has been swept clean- flooring is next.
Painting of Library will be complete early next week. Bring on the flooring and we will be go- to- go.
Gym- Once metal duct installed and painted. Good to go re- flooring
Ceiling to be painted and benches installed- change rooms

We are getting close as next week will be very busy. The team has worked very hard and command full kudos.

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: