Thomas Merton – Feb 6 – renovation update

Saw-cut of floors appear to be complete- waiting for underground plumbing.
Floors ready for underground piping.

Thought: recommend curbs re- RTU be delivered ASAP. This would allow us to remove existing units and roof in new curbs. Once Roof Curbs are in place would allow us to run all interior Metal Duct. This would expedite our schedule.