St. Nicholas- Feb 14 2020 update

The guys are working this week-end finishing the main entrance and library. I will be returning on Tues to record progress.

Our intent is to complete paneling [wood] – once complete allows us to remove safety fence.
[Library] I understand counter tops to be arriving Friday afternoon. Installation is needed as the school would Like to unpack their boxes and place books etc on new counter tops.