Addition
plywood parapet /roof/ ongoing. George Roque Roofing is on deck
Aerloc, door frame needed / courtyard / allowing masonry contractor starting brick veneer. AVB Spray also needs to be applied. The intent is to complete brick veneer / courtyard/ and then proceed to exterior
New Cafeteria
Masonry contractor will build 2 load bearing walls allowing Steel being erected. This area seems slow as per progress.
Child Care
I am told all footings and foundation walls will be in place by Friday – underground piping to follow.
See video – Best viewed on a large screen