Bishop Reding- Feb 26 – construction update

Courtyard- door frame is now in place allowing masonry contractor starting brick veneer
I am told masonry contractor has received material needed/ to build the last load bearing wall. Once built will allow steel contractor /Mirage/ to erect steel. Masonry wall scheduled for this week/ weather permitting.
addition- we need to be watertight ASAP
New Childcare – update