Bishop Reding March 3/20- construction progress

New Cafeteria -Masonry contractor is onsite / building load bearing wall. Once built, allows our friends from Mirage to install steel
Childcare- sanitary and storm pipe are now in place. We are excavating our final footing and scheduled to pour this afternoon. Footings would then be 100% complete. Once footings are complete / coring of rebar Next.
Courtyard- masonry contractor is installing angles. Once installed/ spraying AVB to be applied followed with brick veneer.

I will report on progress tomorrow

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: