Bishop Reding March 3/20- construction progress

New Cafeteria -Masonry contractor is onsite / building load bearing wall. Once built, allows our friends from Mirage to install steel
Childcare- sanitary and storm pipe are now in place. We are excavating our final footing and scheduled to pour this afternoon. Footings would then be 100% complete. Once footings are complete / coring of rebar Next.
Courtyard- masonry contractor is installing angles. Once installed/ spraying AVB to be applied followed with brick veneer.

I will report on progress tomorrow