Bishop Reding- March 4- update progress

Roofers have arrived and are loading the roof. πŸ‘πŸ‘
Cafeteria / Masonry contractor building one of two walls needed to erect steel. We are pushing for steel / Mon – Tues of next week.
Childcare – Pouring last of our footings. Rebar to be cored tomorrow- Masonry contractor to mobilize on Friday. After foundation walls are in place allows Besseling Mech to install undergrounds
Childcare- footings complete today.
Just 3 hrs later the boys from GRRC are giv-n-er. There are tears in my eyes. Bring on the painters /2 guys and a brush/ Roof drains to be connected. Good job GRRC.
Angles are being installed. Blue skin nextπŸ‘
Detail of angle fastened to Wall brackets is brilliant. Todd said this is the best way installing angle he has seen. You heard It from the guy who knows.πŸ‘πŸ‘πŸ‘