Bishop Reding – March 6/20 update

Childcare- building of foundation wall has been delayed as /Coring / Of rebar is not in place. Masonry contractor to mobilize when rebar is in place.
Rebar needed allowing foundation walls being built
New cafeteria- Masonry contractor near completion / building / load bearing wall supporting steel. Our friends from Mirage are on deck first of next week.
Courtyard – Opening is being created allowing masonry contractor access – blue skin – AVB spray- brick veneer. Masonry contractor is starting here /courtyard/ then proceed to exterior.
Thought: let’s start thinking about placement of Roof Top Units.
Roof is progressing well. I am told they will be working tomorrow.
Painters are onsite.👍

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: