Bishop Reding- March 11/20 – update

Childcare – rebar is now in place and water has been pumped. Waiting for masonry contractor/ foundation walls
Cafeteria- masonry contractor has just completed final wall- I am told Mirage Steel arrives Tuesday.
Cafeteria- waiting for Mirage Steel.
GRRC – near completionđź‘Ť
watertight
Roof Drains are being connected. Interior watertight by tomorrow at the latest.
DrainLand working on connection – street
Addition 2nd floor – March 11/20