Nelson High School- March 23/20 – construction update

CPP Room- plumbers are installing undergrounds
Stone is being placed / new parking area
Addition- stone has now been placed/ building footprint/ – masonry contractor can now proceed above ground.

Today was a rain day resulting in no exterior activity. Work on the cafeteria / footings/ continues when the weather breaks.

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.