Bishop Reding – March 25/20 – construction update.

Painters onsite painting door frames and starting walls tomorrow. Childcare now backfilled SOG scheduled for next week. Brick veneer starting in the courtyard.

Note: all scheduling and coordination is by Mario [Percon} Too many cooks in the kitchen / me included