Bishop Reding – April 1/20- update

Childcare – 3/4 stone is now being placed prior to SOG. Once slab is poured allows masonry contractor to build above ground.
Cafeteria- Mirage Steel is onsite erecting steel
Addition / Courtyard- Brick veneer near completion scheduled for completion Friday nite. Landscape contractor is on board and will be onsite soon.
Addition exterior- Brick veneer is progressing well and should be wrapping up by the end of this month / weather permitting.
Addition- light fixtures are now onsite waiting for T-bar ceilings.
Addition- remaining locker base to be poured ASAP.
Work is Progressing Well

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

1 thought on “Bishop Reding – April 1/20- update

  1. Donald Trump says:

    Masons crashed that foundation in one day why’s it taking so long to get back fill done Larry??

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: