Thomas Merton- May 15/20- Reno Update

0 Comments

All concrete floors have been patched.
Contractor has confirmed dowels were installed prior to pour.
I am told Drywall Contractor will be onsite Tues.
TYPICAL CEILINGS – HALLWAY
Installing Boilers
Pads have been poured – placement of circulating pumps.