Thomas Merton May 22/20 renovation update

Drywall Contractor is onsite erecting steel studs.
Drywall contractor has started boarding of walls.
Ceilings are coming together – ceiling tile and placement of light fixtures.
All concrete floors have been 100% poured.
Mechanical Contractor starting placement of Equipment.

I believe we have ripped out most equipment and material as we start to rebuild. Duct is being placed in ceilings, Drywall contractor is onboard, and new lighting fixtures are being placed within T-bar. We are going in the right direction.