Bishop Reding – May 25/20 update construction

Addition

Main Floor- framing of T-bar ceilings near completion
Classrooms- lighting fixtures now in place.
Ceramic tile now onsite- corridors.
Railings in place- stairwell
Millwork- metal cabinets onsite.

Going Forward

Painters are working 2nd floor. Main floor is ready for ceramic tile . Flooring needed classrooms. Followed with Millwork

We are ready for whiteboard and tack board – classrooms / Now!

Installation of lockers 1st week of July

Hanging classroom doors Aug 1st.

Cafeteria

Looking out at New Entrance.
New Kitchen
New Cafeteria

Childcare

Exterior walls have now been erected.
All walls scheduled for completion middle of next week . Ready for steel is next.
Note: steel columns must be in place allowing masonry walls to be complete.