*

merry christmas

Merry Christmas

Thomas Merton – June 4/20 update

As per schedule, it was agreed July 20/20 was the “Drop Dead Date” ensuring all T-bar ceilings are in place – complete with ceiling tiles and light fixtures. Therefore: All work above ceilings and drywall partitions must be complete / no later than a July 10th.

Drywall contractor onsite building walls with mud being applied.
Connection needed boilers and pumps???🐢🐢

Conclusion- many tasks needed prior to July 20th. “May The Force Be With Us” We will be watching👀

Author: Larry Arbuckle

Working a lifetime in construction has taught me communication is everything. Flying drones gives me the edge on seeing construction progress from above. Every picture tells a story and a video tells a thousand stories.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: