Thomas Merton – June 4/20 update

As per schedule, it was agreed July 20/20 was the “Drop Dead Date” ensuring all T-bar ceilings are in place – complete with ceiling tiles and light fixtures. Therefore: All work above ceilings and drywall partitions must be complete / no later than a July 10th.

Drywall contractor onsite building walls with mud being applied.
Connection needed boilers and pumps???🐢🐢

Conclusion- many tasks needed prior to July 20th. “May The Force Be With Us” We will be watching👀