Bishop Reding – June 8/20 – construction progress

Addition- north/west corner
Addition south/west corner
New Front Entrance
New Cafeteria
Childcare South/East Corner- We need windows Aerloc
Chidcare North-East Corner -We need windows Aerloc
New Courtyard

Addition- Placement of Ceramic Tile – main floor is ongoing / Installation of Tackboard has started / Metal Duct ongoing 2nd floor/ flooring classrooms starting soon/ Fire Verification date needed.

Childcare- Masonry contractor building interior walls / Installation OWSJ [roof] continues. Placement of metal deck -soon

Cafeteria- Preparing for SOG / Work continues re- parapet [roof]

Addition -3 months remaining.