Classrooms- I am told Monday we start building bulk heads around heat pumps followed by framing of T- bar ceilings. Also, flooring tile arrives this week. On Monday we start our finishes. Painter and drywall contractor /muddling/ need to be onboard.New Heat Pumps – office
On Monday we start putting this place back together starting with framing of T-bar ceilings in classrooms. Mechanical contractor needs to stay ahead of us. As per schedule / all ceilings to be complete prior to July 20th.