Bishop Reding- June 12/20 construction update

Childcare- waiting for metal deck – roof.
Cafeteria -Parapet / plywood/ is ongoing.
Demolition continues / Admin Office.
2nd floor classrooms- T- bar [ceilings] installation has started👍
I am told full permanent power will be initiated next week.