Nelson HS – June 12/20 – construction update

Manufacturing Rm- we are in need of Windows [Aerloc] I am told plywood [parapet] arrives Monday and installation soon after.
Manufacturing Rm- I am told we are preparing to pour SOG next week๐Ÿ‘๐Ÿ‘
We are now erecting steel Library/Cafeteria. Masonry Contractor is onsite this week-end /building walls.
New Parking area.

We are pushing the Manufacturing and CPP rooms for completion prior to September. Cafeteria/Library to follow- soon after. โ€˜The Skates Are Onโ€ time to giddy up.